get_Optimistic
get_Optimistic
Gets the percentage of the most likely task duration which can happen in the best possible project scenario. The default value is 75, which means that if the estimated specified task duration is 4 days then the optimistic duration will be 3 days.
Returns: int32_t Aspose::Tasks::RiskAnalysis::
get_Optimistic()