## GetFinishDateByStartAndWork (1 of 2) {#getfinishdatebystartandwork_1}

Calculates the date when the specified amount of work time will pass according to the calendar.

**Returns:** Finish date.

```cpp
GetFinishDateByStartAndWork(System::DateTime start, Duration work)
```

| Parameter | Description |
| --- | --- |
| start | Start date. |
| work | Work duration. |

---

## GetFinishDateByStartAndWork (2 of 2) {#getfinishdatebystartandwork_2}

Calculates the date when the specified amount of work time will pass according to the calendar.

**Returns:** Finish date.

```cpp
GetFinishDateByStartAndWork(System::DateTime start, System::TimeSpan work)
```

| Parameter | Description |
| --- | --- |
| start | Start date. |