Fields
Modifier and Type |
Field |
Description |
static Key<String,Integer> |
ACTIVITY_ID |
Represents activity id field - a task's unique identifier used by Primavera.
|
static Key<BigDecimal,Integer> |
ACTUAL_COST |
Costs incurred for work already performed by resources on their tasks, together with any other recorded costs
associated with the task.
|
static Key<Duration,Integer> |
ACTUAL_DURATION |
The span of actual working time for a task, based on the scheduled duration and current remaining work or percent
complete.
|
static Key<Date,Integer> |
ACTUAL_FINISH |
The date when a task was completed.
|
static Key<BigDecimal,Integer> |
ACTUAL_OVERTIME_COST |
Costs incurred for overtime work already performed on tasks by assigned resources.
|
static Key<Duration,Integer> |
ACTUAL_OVERTIME_WORK |
The actual amount of overtime work already performed by resources assigned to tasks.
|
static Key<Duration,Integer> |
ACTUAL_OVERTIME_WORK_PROTECTED |
The duration through which actual overtime work is protected.
|
static Key<Date,Integer> |
ACTUAL_START |
The date and time that a task actually began.
|
static Key<Duration,Integer> |
ACTUAL_WORK |
The amount of work that has already been done by resources assigned to tasks.
|
static Key<Duration,Integer> |
ACTUAL_WORK_PROTECTED |
The duration through which actual work is protected.
|
static Key<Double,Integer> |
ACWP |
Costs incurred for work already done on a task, up to the project status date or today's date.
|
static Key<Double,Integer> |
BCWP |
The cumulative value of the task's percent complete multiplied by the time phased baseline costs.
|
static Key<Double,Integer> |
BCWS |
The cumulative time phased baseline costs up to the status date or today's date.
|
static Key<BigDecimal,Integer> |
BUDGET_COST |
Budget costs for budget cost resources.
|
static Key<Duration,Integer> |
BUDGET_WORK |
Budget work for budget work and material resources.
|
static Key<Calendar,Integer> |
CALENDAR |
The task calendar.
|
static Key<Date,Integer> |
COMMITMENT_FINISH |
The finish date of a delivery.
|
static Key<Date,Integer> |
COMMITMENT_START |
The start date of a delivery.
|
static Key<Integer,Integer> |
COMMITMENT_TYPE |
Determines whether a task has an associated delivery or
a dependency on an associated delivery.
|
static Key<Date,Integer> |
CONSTRAINT_DATE |
The specific date associated with the constraint type.
|
static Key<Integer,Integer> |
CONSTRAINT_TYPE |
Provides choices for the type of constraint that can be applied for scheduling a task.
|
static Key<String,Integer> |
CONTACT |
The name of an individual responsible for a task.
|
static Key<BigDecimal,Integer> |
COST |
The total scheduled or projected cost for a task based on costs already incurred for work performed by resources
assigned to the tasks, in addition to the costs planned for the remaining work.
|
static Key<Double,Integer> |
COST_VARIANCE |
The difference between the baseline cost and total cost for a task, resource, or assignment.
|
static Key<Date,Integer> |
CREATED |
The date when a task was created.
|
static Key<Double,Integer> |
CV |
The difference between the baseline cost and total cost for a task.
|
static Key<Date,Integer> |
DEADLINE |
A target date that indicates when a task is to be completed.
|
static Key<NullableBool,Integer> |
DISPLAY_AS_SUMMARY |
Determines whether the task should be displayed as a summary task.
|
static Key<Boolean,Integer> |
DISPLAY_ON_TIMELINE |
Specifies whether a task should be displayed on a timeline view.
|
static Key<Duration,Integer> |
DURATION |
The total span of active working time for a task as entered or as calculated by Microsoft Project based on start
date, finish date, calendars, and other scheduling factors.
|
static Key<Integer,Integer> |
DURATION_FORMAT |
Task duration format.
|
static Key<String,Integer> |
DURATION_TEXT |
Returns the task's duration text.
|
static Key<Duration,Integer> |
DURATION_VARIANCE |
The difference between the baseline duration of a task and the total duration (current estimate) of a task.
|
static Key<Date,Integer> |
EARLY_FINISH |
The earliest date that a task could possibly finish, based on early finish dates of predecessor and successor
tasks, other constraints, and any leveling delay.
|
static Key<Date,Integer> |
EARLY_START |
The earliest date that a task could possibly begin, based on the early start dates of predecessor and successor
tasks and other constraints.
|
static Key<Integer,Integer> |
EARNED_VALUE_METHOD |
Determines whether the % Complete or Physical % Complete field should be used to calculate budgeted cost of work
performed (BCWP).
|
static Key<Integer,Integer> |
EXTERNAL_ID |
If a task is an external task it contains the task's external Id.
|
static Key<String,Integer> |
EXTERNAL_TASK_PROJECT |
The source location and task identifier of an external task.
|
static Key<Date,Integer> |
FINISH |
The scheduled finish date of a task.
|
static Key<Integer,Integer> |
FINISH_SLACK |
Deprecated.
|
static Key<TimeDelta,Integer> |
FINISH_SLACK_TIME_SPAN |
The duration (in seconds) between the Early Finish and Late Finish dates.
|
static Key<String,Integer> |
FINISH_TEXT |
Returns the task's finish text.
|
static Key<Duration,Integer> |
FINISH_VARIANCE |
The time that represents the difference between the baseline finish date of a task or assignment and its current
finish date.
|
static Key<Double,Integer> |
FIXED_COST |
Shows any non resource task expense.
|
static Key<Integer,Integer> |
FIXED_COST_ACCRUAL |
Determines choices for how and when fixed costs are to be charged, or accrued, to the cost of a task.
|
static Key<Integer,Integer> |
FREE_SLACK |
Deprecated.
|
static Key<TimeDelta,Integer> |
FREE_SLACK_TIME_SPAN |
The time (in seconds) that a task can be delayed without delaying any successor tasks.
|
static Key<String,Integer> |
GUID |
The generated unique identification codes for a task.
|
static Key<NullableBool,Integer> |
HAS_OVERALLOCATED_RESOURCE |
Indicates whether the task has an resource assigned which has more work on assigned tasks than can be completed
within normal working capacity.
|
static Key<NullableBool,Integer> |
HIDE_BAR |
Determines whether the Gantt bar of a task is hidden when displayed in Microsoft Project.
|
static Key<String,Integer> |
HYPERLINK |
The title or explanatory text for a hyperlink associated with a task.
|
static Key<String,Integer> |
HYPERLINK_ADDRESS |
The address for a hyperlink associated with a task.
|
static Key<String,Integer> |
HYPERLINK_SUB_ADDRESS |
The specific location in a document in a hyperlink associated with a task.
|
static Key<Integer,Integer> |
ID |
The position identifier of a task within the list of tasks.
|
static Key<NullableBool,Integer> |
IGNORE_RESOURCE_CALENDAR |
Determines whether the scheduling of the task considers the calendars of the resources assigned to the task.
|
static Key<Boolean,Integer> |
IGNORE_WARNINGS |
Indicates whether to hide the schedule conflict warning indicator in Microsoft Project.
|
static Key<NullableBool,Integer> |
IS_ACTIVE |
Determines whether a task is active.
|
static Key<NullableBool,Integer> |
IS_CRITICAL |
Determines whether a task is on the critical path.
|
static Key<NullableBool,Integer> |
IS_EFFORT_DRIVEN |
Determines whether the scheduling for the task is effort-driven scheduling.
|
static Key<NullableBool,Integer> |
IS_ESTIMATED |
Determines whether a task is estimated.
|
static Key<NullableBool,Integer> |
IS_EXPANDED |
Determines whether a summary task is expanded or not in GanttChart view.
|
static Key<Boolean,Integer> |
IS_EXTERNAL_TASK |
Determines whether a task is external.
|
static Key<NullableBool,Integer> |
IS_MANUAL |
Determines whether a task is manually scheduled.
|
static Key<Boolean,Integer> |
IS_MARKED |
Shows whether a task is marked for further action or identification of some kind.
|
static Key<NullableBool,Integer> |
IS_MILESTONE |
Determines whether a task is a milestone.
|
static Key<NullableBool,Integer> |
IS_NULL |
Determines whether a task is a null task.
|
static Key<NullableBool,Integer> |
IS_OVERALLOCATED |
Indicates whether any of the assigned resources on a task is assigned to more work on the task than can be done
withing the normal working capacity.
|
static Key<NullableBool,Integer> |
IS_PUBLISHED |
Determines whether the current task should be published to Project Server with the rest of the project.
|
static Key<NullableBool,Integer> |
IS_RECURRING |
Determines whether a task is part of a series of recurring tasks.
|
static Key<NullableBool,Integer> |
IS_RESUME_VALID |
Determines whether a task can be resumed.
|
static Key<NullableBool,Integer> |
IS_ROLLUP |
Determines whether information about the subtask Gantt bars will be rolled up to the summary task bar.
|
static Key<Boolean,Integer> |
IS_SUBPROJECT |
Determines whether a task is an inserted project.
|
static Key<NullableBool,Integer> |
IS_SUBPROJECT_READ_ONLY |
Determines whether a subproject is read-only.
|
static Key<Boolean,Integer> |
IS_SUMMARY |
Determines whether a task is a summary task.
|
static Key<Date,Integer> |
LATE_FINISH |
The latest date that a task can finish without delaying the finish of the project.
|
static Key<Date,Integer> |
LATE_START |
The latest date that a task can start without delaying the finish of the project.
|
static Key<NullableBool,Integer> |
LEVEL_ASSIGNMENTS |
Determines whether the leveling function can delay and split individual assignments in order to resolve over
allocations.
|
static Key<NullableBool,Integer> |
LEVELING_CAN_SPLIT |
Determines whether the resource leveling function can cause splits on remaining work on this task.
|
static Key<Duration,Integer> |
LEVELING_DELAY |
The time that a task is to be delayed from its early start date because of resource leveling.
|
static Key<Integer,Integer> |
LEVELING_DELAY_FORMAT |
The format of expressing the duration of a delay.
|
static Key<Duration,Integer> |
MANUAL_DURATION |
Defines manually scheduled duration of a task.
|
static Key<Date,Integer> |
MANUAL_FINISH |
Defines manually scheduled finish of a task.
|
static Key<Date,Integer> |
MANUAL_START |
Defines manually scheduled start of a task.
|
static Key<String,Integer> |
NAME |
A task's name.
|
static Key<String,Integer> |
NOTES_RTF |
The text notes in RTF format.
|
static Key<String,Integer> |
NOTES_TEXT |
Notes' plain text extracted from RTF data.
|
static Key<Integer,Integer> |
OUTLINE_LEVEL |
The outline level of a task.
|
static Key<String,Integer> |
OUTLINE_NUMBER |
The number that represents a task's position in the hierarchical outline structure.
|
static Key<BigDecimal,Integer> |
OVERTIME_COST |
The total overtime cost for a task, for a resource on all assigned tasks, or for a resource assignment.
|
static Key<Duration,Integer> |
OVERTIME_WORK |
The amount of overtime scheduled to be performed by all resources assigned to a task.
|
static Key<Integer,Integer> |
PERCENT_COMPLETE |
The current status of a task, expressed as the percentage of the task's duration that has been completed.
|
static Key<Integer,Integer> |
PERCENT_WORK_COMPLETE |
The current status of a task expressed as the percentage of work that has been completed.
|
static Key<Integer,Integer> |
PHYSICAL_PERCENT_COMPLETE |
Percent complete value that can be be used as an alternative for calculating budgeted cost of work performed
(BCWP).
|
static Key<Date,Integer> |
PRELEVELED_FINISH |
The finish date of a task as it was before resource leveling was done.
|
static Key<Date,Integer> |
PRELEVELED_START |
The start date of a task as it was before resource leveling was done.
|
static Key<Integer,Integer> |
PRIORITY |
The level of importance given to a task, which in turn indicates how readily a task or assignment can be delayed
or split during resource leveling.
|
static Key<Duration,Integer> |
REGULAR_WORK |
The total amount of non overtime work scheduled to be performed by resources.
|
static Key<BigDecimal,Integer> |
REMAINING_COST |
The remaining scheduled expense that will be incurred in completing the remaining scheduled work.
|
static Key<Duration,Integer> |
REMAINING_DURATION |
The time that is required to complete the unfinished part of a task.
|
static Key<BigDecimal,Integer> |
REMAINING_OVERTIME_COST |
The remaining scheduled overtime expense for a task.
|
static Key<Duration,Integer> |
REMAINING_OVERTIME_WORK |
The amount of remaining scheduled overtime time.
|
static Key<Duration,Integer> |
REMAINING_WORK |
The time still required to complete a task or set of tasks.
|
static Key<Date,Integer> |
RESUME |
The date that the remaining part of a task is scheduled to resume after entering any progress.
|
static Key<Date,Integer> |
START |
The scheduled start date of a task.
|
static Key<Integer,Integer> |
START_SLACK |
Deprecated.
|
static Key<TimeDelta,Integer> |
START_SLACK_TIME_SPAN |
The duration (in seconds) between the Early Start and Late Start dates.
|
static Key<String,Integer> |
START_TEXT |
Returns the task's start text.
|
static Key<Duration,Integer> |
START_VARIANCE |
The time that represents the difference between a baseline start date of a task or assignment and its currently
scheduled start date.
|
static Key<String,Integer> |
STATUS_MANAGER |
The name of the enterprise resource who is to receive status updates for the current task from resources.
|
static Key<Date,Integer> |
STOP |
The date that represents the end of the actual portion of a task.
|
static Key<String,Integer> |
SUBPROJECT_NAME |
The source location of a subproject.
|
static Key<Double,Integer> |
SV |
The earned value schedule variance, through the project status date.
|
static Key<Integer,Integer> |
TOTAL_SLACK |
Deprecated.
|
static Key<TimeDelta,Integer> |
TOTAL_SLACK_TIME_SPAN |
The time a task's finish date can be delayed without delaying the project's finish date.
|
static Key<Integer,Integer> |
TYPE |
The type of a task.
|
static Key<Integer,Integer> |
UID |
The unique Id of a task.
|
static Key<Boolean,Integer> |
WARNING |
Represents the flag which indicates that task has schedule discrepancies.
|
static Key<String,Integer> |
WBS |
Work breakdown structure (WBS) codes.
|
static Key<String,Integer> |
WBS_LEVEL |
The rightmost WBS level of a task.
|
static Key<Duration,Integer> |
WORK |
The total time scheduled on a task for all assigned resources.
|
static Key<Duration,Integer> |
WORK_VARIANCE |
The difference between baseline work of a task and the currently scheduled work.
|