PrimaveraRelationshipLagCalendar

PrimaveraRelationshipLagCalendar enumeration

Specifies which calendar to use for scheduling Relationship Lag in Primavera projects.

public enum PrimaveraRelationshipLagCalendar

Values

NameValueDescription
Predecessor0Use predecessor activity calendar
Successor1Use successor activity calendar
Calendar24Hour2Use 24 Hours calendar
Default3Use project default calendar