Milestone

Asn.Milestone field

Determines whether the assignment is a milestone.

public static readonly Key<bool, AsnKey> Milestone;

Examples

Shows how to read Asn.Milestone property.

var project = new Project();

var task = project.RootTask.Children.Add("Task 1");
task.Set(Tsk.Start, new DateTime(2000, 1, 3, 8, 0, 0));
task.Set(Tsk.Duration, project.GetDuration(8));

var resource = project.Resources.Add("Resource 1");

var assignment = project.ResourceAssignments.Add(task, resource);

Console.WriteLine("Milestone: " + assignment.Get(Asn.Milestone));