Calendar.GetNextWorkingDayStart
Calendar.GetNextWorkingDayStart method
Calculates next working day start from the date.
public DateTime GetNextWorkingDayStart(DateTime date)
Parameter | Type | Description |
---|---|---|
date | DateTime | The date to get next working day start for. |
Return Value
Next working day start DateTime.
Examples
Shows how to get a next working day start by using a calendar.
var project = new Project(DataDir + "Project1.mpp");
var calendar = project.Calendars.GetByUid(1);
// get next working day start (weekend is skipped)
var nextWorkingDayStart = calendar.GetNextWorkingDayStart(new DateTime(2020, 4, 10, 13, 0, 0));
// 13 April 2020 9:00 AM will be printed
Console.WriteLine(nextWorkingDayStart);