Rsc.PercentWorkComplete
Rsc.PercentWorkComplete field
The percentage of work completed across all tasks.
public static readonly Key<int, RscKey> PercentWorkComplete;
Examples
Shows how to read resource percent work complete.
var project = new Project(DataDir + "ResourcePercentWorkComplete.mpp");
// Display work percentage completion for all resources
foreach (var res in project.Resources)
{
if (res.Get(Rsc.Name) != null)
{
Console.WriteLine(res.Get(Rsc.PercentWorkComplete));
}
}
See Also
- struct Key<T,K>
- enum RscKey
- class Rsc
- namespace Aspose.Tasks
- assembly Aspose.Tasks