Rsc.SV field

The earned value schedule variance, through the project status date. SV is the difference between budgeted cost of work performed (BCWP) and budgeted cost of work scheduled (BCWS).

public static readonly Key<double, RscKey> SV;

Examples

Shows how to read resource costs.

var project = new Project(DataDir + "ResourceCosts.mpp");

// Display all resources costs
foreach (var res in project.Resources)
{
    if (res.Get(Rsc.Name) == null)
    {
        continue;
    }

    Console.WriteLine(res.Get(Rsc.Cost));
    Console.WriteLine(res.Get(Rsc.ACWP));
    Console.WriteLine(res.Get(Rsc.BCWS));
    Console.WriteLine(res.Get(Rsc.BCWP));

    // CV = BCWP - ACWP
    Console.WriteLine(res.Get(Rsc.CV));

    // SV = BCWP - BCWS
    Console.WriteLine(res.Get(Rsc.SV));
}