TaskBaseline.Duration
Contents
[
Hide
]TaskBaseline.Duration property
Gets or sets the scheduled duration of the task when the baseline was saved.
public Duration Duration { get; set; }
Examples
Shows how to get access to a baseline information.
var project = new Project();
// Creating TaskBaseline
var task = project.RootTask.Children.Add("Task");
project.SetBaseline(BaselineType.Baseline);
// Display task baseline duration
var baseline = task.Baselines.ToList()[0];
Console.WriteLine("Baseline Start: {0}", baseline.Start);
Console.WriteLine("Baseline duration: {0}", baseline.Duration);
Console.WriteLine("Baseline duration format: {0}", baseline.Duration.TimeUnit);
Console.WriteLine("Is it estimated duration?: {0}", baseline.EstimatedDuration);
Console.WriteLine("Baseline Finish: {0}", baseline.Finish);
// value indicating whether this is an Interim Baseline
Console.WriteLine("Interim: {0}", baseline.Interim);
Console.WriteLine("Fixed Cost: {0}", baseline.FixedCost);
// print timephased data of task baseline
Console.WriteLine("Number of timephased items: " + baseline.TimephasedData.Count);
foreach (var data in baseline.TimephasedData)
{
Console.WriteLine(" Uid: " + data.Uid);
Console.WriteLine(" Start: " + data.Start);
Console.WriteLine(" Finish: " + data.Finish);
}
See Also
- struct Duration
- class TaskBaseline
- namespace Aspose.Tasks