TaskLink.CrossProjectName
Contents
[
Hide
]TaskLink.CrossProjectName property
Gets or sets the external predecessor project.
public string CrossProjectName { get; set; }
Examples
Shows how to find cross project task links.
var project = new Project(DataDir + "GetCrossProjectTaskLinks.mpp");
// Check cross project task links
foreach (var taskLink in project.TaskLinks)
{
Console.WriteLine("Task Link: " + taskLink.ToString());
if (taskLink.IsCrossProject)
{
Console.WriteLine(taskLink.CrossProjectName);
}
}
Shows how to create cross project task link - link to task in another (external) project.
Project project = new Project();
var summary = project.RootTask.Children.Add("Summary Task");
// In order to create a link to a task from another project we should create
// its duplicate (or "external") task in the current project.
Task t2 = summary.Children.Add("External Task");
t2.Set(Tsk.ExternalTaskProject, "ExternalProject.mpp"); // here we set path to external project's MPP file.
t2.Set(Tsk.ExternalId, 1); // Set External task's Id.
t2.Set(Tsk.ExternalUid, 2); // External task's Unique Id should be set.
t2.Set(Tsk.IsExternalTask, true);
t2.Set(Tsk.IsManual, new NullableBool(false));
t2.Set(Tsk.IsSummary, false);
Task t = summary.Children.Add("Task");
TaskLink link = project.TaskLinks.Add(t2, t);
link.IsCrossProject = true;
link.LinkType = TaskLinkType.FinishToStart;
link.CrossProjectName = "ExternalProject.mpp\\\\1"; // <- here external task's Id is used.
See Also
- class TaskLink
- namespace Aspose.Tasks
- assembly Aspose.Tasks