Enum TaskUsageViewField
Contents
[
Hide
]TaskUsageViewField enumeration
Represents possible fields in TaskUsageView object.
public enum TaskUsageViewField
Values
| Name | Value | Description |
|---|---|---|
| Undefined | -1 | Indicates Undefined task usage view field. |
| Work | 0 | Indicates Work task usage view field. |
| OvertimeWork | 1 | Indicates Overtime Work task usage view field. |
| ActualWork | 2 | Indicates Actual Work task usage view field. |
| ActualOvertimeWork | 3 | Indicates Actual Overtime Work task usage view field. |
| CumulativeWork | 4 | Indicates Cumulative Work task usage view field. |
| BaselineWork | 5 | Indicates Baseline Work task usage view field. |
| Overallocation | 6 | Indicates Overallocation task usage view field. |
| PercentAllocation | 7 | Indicates Percent Allocation task usage view field. |
| PeakUnits | 8 | Indicates Peak Units task usage view field. |
| Cost | 9 | Indicates Cost task usage view field. |
| FixedCost | 10 | Indicates Fixed Cost task usage view field. |
| ActualCost | 11 | Indicates Actual Cost task usage view field. |
| BaselineCost | 12 | Indicates Baseline Cost task usage view field. |
| CumulativeCost | 13 | Indicates Cumulative Cost task usage view field. |
| BCWS | 14 | Indicates BCWS task usage view field. |
| BCWP | 15 | Indicates BCWP task usage view field. |
| ACWP | 16 | Indicates ACWP task usage view field. |
| SV | 17 | Indicates SV task usage view field. |
| CV | 18 | Indicates CV task usage view field. |
| RegularWork | 19 | Indicates Regular Work task usage view field. |
| PercentComplete | 20 | Indicates Percent Complete task usage view field. |
| CumulativePercentComplete | 21 | Indicates Cumulative Percent Complete task usage view field. |
| Baseline1Work | 22 | Indicates Baseline1 Work task usage view field. |
| Baseline1Cost | 23 | Indicates Baseline1 Cost task usage view field. |
| Baseline2Work | 24 | Indicates Baseline2 Work task usage view field. |
| Baseline2Cost | 25 | Indicates Baseline2 Cost task usage view field. |
| Baseline3Work | 26 | Indicates Baseline3 Work task usage view field. |
| Baseline3Cost | 27 | Indicates Baseline3 Cost task usage view field. |
| Baseline4Work | 28 | Indicates Baseline4 Work task usage view field. |
| Baseline4Cost | 29 | Indicates Baseline4 Cost task usage view field. |
| Baseline5Work | 30 | Indicates Baseline5 Work task usage view field. |
| Baseline5Cost | 31 | Indicates Baseline5 Cost task usage view field. |
| Baseline6Work | 32 | Indicates Baseline6 Work task usage view field. |
| Baseline6Cost | 33 | Indicates Baseline6 Cost task usage view field. |
| Baseline7Work | 34 | Indicates Baseline7 Work task usage view field. |
| Baseline7Cost | 35 | Indicates Baseline7 Cost task usage view field. |
| Baseline8Work | 36 | Indicates Baseline8 Work task usage view field. |
| Baseline8Cost | 37 | Indicates Baseline8 Cost task usage view field. |
| Baseline9Work | 38 | Indicates Baseline9 Work task usage view field. |
| Baseline9Cost | 39 | Indicates Baseline9 Cost task usage view field. |
| Baseline10Work | 40 | Indicates Baseline10 Work task usage view field. |
| Baseline10Cost | 41 | Indicates Baseline10 Cost task usage view field. |
| ActualFixedCost | 42 | Indicates Actual Fixed Cost task usage view field. |
| CPI | 43 | Indicates CPI task usage view field. |
| SPI | 44 | Indicates SPI task usage view field. |
| CVPercent | 45 | Indicates CV Percent task usage view field. |
| SVPercent | 46 | Indicates SV Percent task usage view field. |
| BudgetWork | 47 | Indicates Budget Work task usage view field. |
| BudgetCost | 48 | Indicates Budget Cost task usage view field. |
| BaselineBudgetWork | 49 | Indicates Baseline Budget Work task usage view field. |
| BaselineBudgetCost | 50 | Indicates Baseline Budget Cost task usage view field. |
| Baseline1BudgetWork | 51 | Indicates Baseline1 Budget Work task usage view field. |
| Baseline1BudgetCost | 52 | Indicates Baseline1 Budget Cost task usage view field. |
| Baseline2BudgetWork | 53 | Indicates Baseline2 Budget Work task usage view field. |
| Baseline2BudgetCost | 54 | Indicates Baseline2 Budget Cost task usage view field. |
| Baseline3BudgetWork | 55 | Indicates Baseline3 Budget Work task usage view field. |
| Baseline3BudgetCost | 56 | Indicates Baseline3 Budget Cost task usage view field. |
| Baseline4BudgetWork | 57 | Indicates Baseline4 Budget Work task usage view field. |
| Baseline4BudgetCost | 58 | Indicates Baseline4 Budget Cost task usage view field. |
| Baseline5BudgetWork | 59 | Indicates Baseline5 Budget Work task usage view field. |
| Baseline5BudgetCost | 60 | Indicates Baseline5 Budget Cost task usage view field. |
| Baseline6BudgetWork | 61 | Indicates Baseline6 Budget Work task usage view field. |
| Baseline6BudgetCost | 62 | Indicates Baseline6 Budget Cost task usage view field. |
| Baseline7BudgetWork | 63 | Indicates Baseline7 Budget Work task usage view field. |
| Baseline7BudgetCost | 64 | Indicates Baseline7 Budget Cost task usage view field. |
| Baseline8BudgetWork | 65 | Indicates Baseline8 Budget Work task usage view field. |
| Baseline8BudgetCost | 66 | Indicates Baseline8 Budget Cost task usage view field. |
| Baseline9BudgetWork | 67 | Indicates Baseline9 Budget Work task usage view field. |
| Baseline9BudgetCost | 68 | Indicates Baseline9 Budget Cost task usage view field. |
| Baseline10BudgetWork | 69 | Indicates Baseline10 Budget Work task usage view field. |
| Baseline10BudgetCost | 70 | Indicates Baseline10 Budget Cost task usage view field. |
| AllTaskRows | 71 | Indicates All Task Rows task usage view field. |
| AllAssignmentRows | 72 | Indicates All Assignment Rows task usage view field. |
Examples
Shows how to work field collection of a TaskUsageView instance.
var project = new Project(DataDir + "TaskUsageView.mpp");
var view = (TaskUsageView)project.Views.ToList()[2];
foreach (var field in view.FieldCollection)
{
Console.WriteLine("Field: " + field);
}
// one can transform collection into a list of TaskUsageViewField
IList<TaskUsageViewField> fields = view.FieldCollection.ToList();
foreach (var field in fields)
{
Console.WriteLine("Field (from the list): " + field);
}
See Also
- namespace Aspose.Tasks
- assembly Aspose.Tasks