Tsk.ActualFinish
Tsk.ActualFinish field
The date when a task was completed.
public static readonly Key<DateTime, TaskKey> ActualFinish;
Examples
Shows that project’ dates are reset in an evaluation mode.
var project = new Project();
// create new tasks
var task1 = project.RootTask.Children.Add("Task1");
task1.Set(Tsk.ActualStart, new DateTime(2000, 2, 10, 8, 0, 0));
task1.Set(Tsk.ActualFinish, new DateTime(2000, 2, 10, 17, 0, 0));
var task2 = project.RootTask.Children.Add("Task2");
task2.Set(Tsk.ActualStart, new DateTime(2000, 2, 10, 8, 0, 0));
task2.Set(Tsk.ActualFinish, new DateTime(2000, 2, 10, 17, 0, 0));
project.Save(OutDir + "EvaluationDateTimeLimitations_out.xml", SaveFileFormat.Xml);
See Also
- struct Key<T,K>
- enum TaskKey
- class Tsk
- namespace Aspose.Tasks
- assembly Aspose.Tasks