Tsk.Cost

Tsk.Cost field

The total scheduled or projected cost for a task based on costs already incurred for work performed by resources assigned to the tasks, in addition to the costs planned for the remaining work.

public static readonly Key<decimal, TaskKey> Cost;

Examples

Shows how to read task costs.

var project = new Project();

// Add task and set cost
var task = project.RootTask.Children.Add("Task");
task.Set(Tsk.Cost, 800);

// Display cost related properties of task
Console.WriteLine(task.Get(Tsk.RemainingCost));
Console.WriteLine(task.Get(Tsk.FixedCost));
Console.WriteLine(task.Get(Tsk.CostVariance));
Console.WriteLine(project.RootTask.Get(Tsk.Cost));
Console.WriteLine(project.RootTask.Get(Tsk.FixedCost));
Console.WriteLine(project.RootTask.Get(Tsk.RemainingCost));
Console.WriteLine(project.RootTask.Get(Tsk.CostVariance));

See Also