FixedCost

Tsk.FixedCost field

Shows any non resource task expense.

public static readonly Key<double, TaskKey> FixedCost;

Examples

Shows how to read task costs.

var project = new Project();

// Add task and set cost
var task = project.RootTask.Children.Add("Task");
task.Set(Tsk.Cost, 800);

// Display cost related properties of task
Console.WriteLine(task.Get(Tsk.RemainingCost));
Console.WriteLine(task.Get(Tsk.FixedCost));
Console.WriteLine(task.Get(Tsk.CostVariance));
Console.WriteLine(project.RootTask.Get(Tsk.Cost));
Console.WriteLine(project.RootTask.Get(Tsk.FixedCost));
Console.WriteLine(project.RootTask.Get(Tsk.RemainingCost));
Console.WriteLine(project.RootTask.Get(Tsk.CostVariance));

See Also