Tsk.PercentWorkComplete
Tsk.PercentWorkComplete field
The current status of a task expressed as the percentage of work that has been completed.
public static readonly Key<int, TaskKey> PercentWorkComplete;
Examples
Shows how to read/write Tsk.PercentWorkComplete property.
var project = new Project();
var task = project.RootTask.Children.Add("Task");
task.Set(Tsk.PercentWorkComplete, 10);
Console.WriteLine("Percent Work Complete: " + task.Get(Tsk.PercentWorkComplete));
See Also
- struct Key<T,K>
- enum TaskKey
- class Tsk
- namespace Aspose.Tasks
- assembly Aspose.Tasks