Tsk.RemainingCost
Tsk.RemainingCost field
The remaining scheduled expense that will be incurred in completing the remaining scheduled work.
public static readonly Key<decimal, TaskKey> RemainingCost;
Examples
Shows how to read task costs.
var project = new Project();
// Add task and set cost
var task = project.RootTask.Children.Add("Task");
task.Set(Tsk.Cost, 800);
// Display cost related properties of task
Console.WriteLine(task.Get(Tsk.RemainingCost));
Console.WriteLine(task.Get(Tsk.FixedCost));
Console.WriteLine(task.Get(Tsk.CostVariance));
Console.WriteLine(project.RootTask.Get(Tsk.Cost));
Console.WriteLine(project.RootTask.Get(Tsk.FixedCost));
Console.WriteLine(project.RootTask.Get(Tsk.RemainingCost));
Console.WriteLine(project.RootTask.Get(Tsk.CostVariance));
See Also
- struct Key<T,K>
- enum TaskKey
- class Tsk
- namespace Aspose.Tasks