Tsk

Inheritance: java.lang.Object

public class Tsk

Represents properties of Task object.

Constructors

ConstructorDescription
Tsk()

Fields

FieldDescription
ACTIVITY_IDRepresents activity id field - a task’s unique identifier used by Primavera.
ACTUAL_COSTCosts incurred for work already performed by resources on their tasks, together with any other recorded costs associated with the task.
ACTUAL_DURATIONThe span of actual working time for a task, based on the scheduled duration and current remaining work or percent complete.
ACTUAL_FINISHThe date when a task was completed.
ACTUAL_OVERTIME_COSTCosts incurred for overtime work already performed on tasks by assigned resources.
ACTUAL_OVERTIME_WORKThe actual amount of overtime work already performed by resources assigned to tasks.
ACTUAL_OVERTIME_WORK_PROTECTEDThe duration through which actual overtime work is protected.
ACTUAL_STARTThe date and time that a task actually began.
ACTUAL_WORKThe amount of work that has already been done by resources assigned to tasks.
ACTUAL_WORK_PROTECTEDThe duration through which actual work is protected.
ACWPCosts incurred for work already done on a task, up to the project status date or today’s date.
BCWPThe cumulative value of the task’s percent complete multiplied by the time phased baseline costs.
BCWSThe cumulative time phased baseline costs up to the status date or today’s date.
BUDGET_COSTBudget costs for budget cost resources.
BUDGET_WORKBudget work for budget work and material resources.
CALENDARThe task calendar.
COMMITMENT_FINISHThe finish date of a delivery.
COMMITMENT_STARTThe start date of a delivery.
COMMITMENT_TYPEDetermines whether a task has an associated delivery or a dependency on an associated delivery.
CONSTRAINT_DATEThe specific date associated with the constraint type.
CONSTRAINT_TYPEProvides choices for the type of constraint that can be applied for scheduling a task.
CONTACTThe name of an individual responsible for a task.
COSTThe total scheduled or projected cost for a task based on costs already incurred for work performed by resources assigned to the tasks, in addition to the costs planned for the remaining work.
COST_VARIANCEThe difference between the baseline cost and total cost for a task, resource, or assignment.
CREATEDThe date when a task was created.
CVThe difference between the baseline cost and total cost for a task.
DEADLINEA target date that indicates when a task is to be completed.
DISPLAY_AS_SUMMARYDetermines whether the task should be displayed as a summary task.
DISPLAY_ON_TIMELINESpecifies whether a task should be displayed on a timeline view.
DURATIONThe total span of active working time for a task as entered or as calculated by Microsoft Project based on start date, finish date, calendars, and other scheduling factors.
DURATION_FORMATTask duration format.
DURATION_TEXTReturns the task’s duration text.
DURATION_VARIANCEThe difference between the baseline duration of a task and the total duration (current estimate) of a task.
EARLY_FINISHThe earliest date that a task could possibly finish, based on early finish dates of predecessor and successor tasks, other constraints, and any leveling delay.
EARLY_STARTThe earliest date that a task could possibly begin, based on the early start dates of predecessor and successor tasks and other constraints.
EARNED_VALUE_METHODDetermines whether the % Complete or Physical % Complete field should be used to calculate budgeted cost of work performed (BCWP).
EXTERNAL_IDIf a task is an external task it contains the task’s external Id.
EXTERNAL_TASK_PROJECTThe source location and task identifier of an external task.
EXTERNAL_UIDContains the external task’s Unique identifier when the task is external.
FINISHThe scheduled finish date of a task.
FINISH_SLACK_TIME_SPANThe duration (in seconds) between the Early Finish and Late Finish dates.
FINISH_TEXTReturns the task’s finish text.
FINISH_VARIANCEThe time that represents the difference between the baseline finish date of a task or assignment and its current finish date.
FIXED_COSTShows any non resource task expense.
FIXED_COST_ACCRUALDetermines choices for how and when fixed costs are to be charged, or accrued, to the cost of a task.
FREE_SLACK_TIME_SPANThe time (in seconds) that a task can be delayed without delaying any successor tasks.
GUIDThe generated unique identification codes for a task.
HAS_OVERALLOCATED_RESOURCEIndicates whether the task has an resource assigned which has more work on assigned tasks than can be completed within normal working capacity.
HIDE_BARDetermines whether the Gantt bar of a task is hidden when displayed in Microsoft Project.
HYPERLINKThe title or explanatory text for a hyperlink associated with a task.
HYPERLINK_ADDRESSThe address for a hyperlink associated with a task.
HYPERLINK_SUB_ADDRESSThe specific location in a document in a hyperlink associated with a task.
IDThe position identifier of a task within the list of tasks.
IGNORE_RESOURCE_CALENDARDetermines whether the scheduling of the task considers the calendars of the resources assigned to the task.
IGNORE_WARNINGSIndicates whether to hide the schedule conflict warning indicator in Microsoft Project.
IS_ACTIVEDetermines whether a task is active.
IS_CRITICALDetermines whether a task is on the critical path.
IS_EFFORT_DRIVENDetermines whether the scheduling for the task is effort-driven scheduling.
IS_ESTIMATEDDetermines whether a task is estimated.
IS_EXPANDEDDetermines whether a summary task is expanded or not in GanttChart view.
IS_EXTERNAL_TASKDetermines whether a task is external.
IS_MANUALDetermines whether a task is manually scheduled.
IS_MARKEDShows whether a task is marked for further action or identification of some kind.
IS_MILESTONEDetermines whether a task is a milestone.
IS_NULLDetermines whether a task is a null task.
IS_OVERALLOCATEDIndicates whether any of the assigned resources on a task is assigned to more work on the task than can be done withing the normal working capacity.
IS_PUBLISHEDDetermines whether the current task should be published to Project Server with the rest of the project.
IS_RECURRINGDetermines whether a task is part of a series of recurring tasks.
IS_RESUME_VALIDDetermines whether a task can be resumed.
IS_ROLLUPDetermines whether information about the subtask Gantt bars will be rolled up to the summary task bar.
IS_SUBPROJECTDetermines whether a task is an inserted project.
IS_SUBPROJECT_READ_ONLYDetermines whether a subproject is read-only.
IS_SUMMARYDetermines whether a task is a summary task.
LATE_FINISHThe latest date that a task can finish without delaying the finish of the project.
LATE_STARTThe latest date that a task can start without delaying the finish of the project.
LEVELING_CAN_SPLITDetermines whether the resource leveling function can cause splits on remaining work on this task.
LEVELING_DELAYThe time that a task is to be delayed from its early start date because of resource leveling.
LEVEL_ASSIGNMENTSDetermines whether the leveling function can delay and split individual assignments in order to resolve over allocations.
MANUAL_DURATIONDefines manually scheduled duration of a task.
MANUAL_FINISHDefines manually scheduled finish of a task.
MANUAL_STARTDefines manually scheduled start of a task.
NAMEA task’s name.
NOTES_RTFThe text notes in RTF format.
NOTES_TEXTNotes’ plain text extracted from RTF data.
OUTLINE_LEVELThe outline level of a task.
OUTLINE_NUMBERThe number that represents a task’s position in the hierarchical outline structure.
OVERTIME_COSTThe total overtime cost for a task, for a resource on all assigned tasks, or for a resource assignment.
OVERTIME_WORKThe amount of overtime scheduled to be performed by all resources assigned to a task.
PERCENT_COMPLETEThe current status of a task, expressed as the percentage of the task’s duration that has been completed.
PERCENT_WORK_COMPLETEThe current status of a task expressed as the percentage of work that has been completed.
PHYSICAL_PERCENT_COMPLETEPercent complete value that can be be used as an alternative for calculating budgeted cost of work performed (BCWP).
PRELEVELED_FINISHThe finish date of a task as it was before resource leveling was done.
PRELEVELED_STARTThe start date of a task as it was before resource leveling was done.
PRIORITYThe level of importance given to a task, which in turn indicates how readily a task or assignment can be delayed or split during resource leveling.
REGULAR_WORKThe total amount of non overtime work scheduled to be performed by resources.
REMAINING_COSTThe remaining scheduled expense that will be incurred in completing the remaining scheduled work.
REMAINING_DURATIONThe time that is required to complete the unfinished part of a task.
REMAINING_OVERTIME_COSTThe remaining scheduled overtime expense for a task.
REMAINING_OVERTIME_WORKThe amount of remaining scheduled overtime time.
REMAINING_WORKThe time still required to complete a task or set of tasks.
RESUMEThe date that the remaining part of a task is scheduled to resume after entering any progress.
STARTThe scheduled start date of a task.
START_SLACK_TIME_SPANThe duration (in seconds) between the Early Start and Late Start dates.
START_TEXTReturns the task’s start text.
START_VARIANCEThe time that represents the difference between a baseline start date of a task or assignment and its currently scheduled start date.
STATUS_MANAGERThe name of the enterprise resource who is to receive status updates for the current task from resources.
STOPThe date that represents the end of the actual portion of a task.
SUBPROJECT_NAMEThe source location of a subproject.
SVThe earned value schedule variance, through the project status date.
TOTAL_SLACK_TIME_SPANThe time a task’s finish date can be delayed without delaying the project’s finish date.
TYPEThe type of a task.
UIDThe unique Id of a task.
WARNINGRepresents the flag which indicates that task has schedule discrepancies.
WBSWork breakdown structure (WBS) codes.
WBS_LEVELThe rightmost WBS level of a task.
WORKThe total time scheduled on a task for all assigned resources.
WORK_VARIANCEThe difference between baseline work of a task and the currently scheduled work.

Tsk()

public Tsk()

ACTIVITY_ID

public static final Key<String,Byte> ACTIVITY_ID

Represents activity id field - a task’s unique identifier used by Primavera. (only applicable to Primavera projects).

ACTUAL_COST

public static final Key<BigDecimal,Byte> ACTUAL_COST

Costs incurred for work already performed by resources on their tasks, together with any other recorded costs associated with the task.

ACTUAL_DURATION

public static final Key<Duration,Byte> ACTUAL_DURATION

The span of actual working time for a task, based on the scheduled duration and current remaining work or percent complete.

ACTUAL_FINISH

public static final Key<Date,Byte> ACTUAL_FINISH

The date when a task was completed.

ACTUAL_OVERTIME_COST

public static final Key<BigDecimal,Byte> ACTUAL_OVERTIME_COST

Costs incurred for overtime work already performed on tasks by assigned resources.

ACTUAL_OVERTIME_WORK

public static final Key<Duration,Byte> ACTUAL_OVERTIME_WORK

The actual amount of overtime work already performed by resources assigned to tasks.

ACTUAL_OVERTIME_WORK_PROTECTED

public static final Key<Duration,Byte> ACTUAL_OVERTIME_WORK_PROTECTED

The duration through which actual overtime work is protected.

ACTUAL_START

public static final Key<Date,Byte> ACTUAL_START

The date and time that a task actually began.

ACTUAL_WORK

public static final Key<Duration,Byte> ACTUAL_WORK

The amount of work that has already been done by resources assigned to tasks.

ACTUAL_WORK_PROTECTED

public static final Key<Duration,Byte> ACTUAL_WORK_PROTECTED

The duration through which actual work is protected.


Reading supported for XML format only.

ACWP

public static final Key<Double,Byte> ACWP

Costs incurred for work already done on a task, up to the project status date or today’s date.

BCWP

public static final Key<Double,Byte> BCWP

The cumulative value of the task’s percent complete multiplied by the time phased baseline costs.

BCWS

public static final Key<Double,Byte> BCWS

The cumulative time phased baseline costs up to the status date or today’s date.

BUDGET_COST

public static final Key<BigDecimal,Byte> BUDGET_COST

Budget costs for budget cost resources. Budget resources are assigned only to the project summary task.

BUDGET_WORK

public static final Key<Duration,Byte> BUDGET_WORK

Budget work for budget work and material resources. Budget resources are assigned only to the project summary task.

CALENDAR

public static final Key<Calendar,Byte> CALENDAR

The task calendar.

COMMITMENT_FINISH

public static final Key<Date,Byte> COMMITMENT_FINISH

The finish date of a delivery.


Reading supported for XML format only.

COMMITMENT_START

public static final Key<Date,Byte> COMMITMENT_START

The start date of a delivery.


Reading supported for XML format only.

COMMITMENT_TYPE

public static final Key<Integer,Byte> COMMITMENT_TYPE

Determines whether a task has an associated delivery or a dependency on an associated delivery.


Reading supported for XML format only.

CONSTRAINT_DATE

public static final Key<Date,Byte> CONSTRAINT_DATE

The specific date associated with the constraint type.

CONSTRAINT_TYPE

public static final Key<Integer,Byte> CONSTRAINT_TYPE

Provides choices for the type of constraint that can be applied for scheduling a task.

CONTACT

public static final Key<String,Byte> CONTACT

The name of an individual responsible for a task.

COST

public static final Key<BigDecimal,Byte> COST

The total scheduled or projected cost for a task based on costs already incurred for work performed by resources assigned to the tasks, in addition to the costs planned for the remaining work.

COST_VARIANCE

public static final Key<Double,Byte> COST_VARIANCE

The difference between the baseline cost and total cost for a task, resource, or assignment.

CREATED

public static final Key<Date,Byte> CREATED

The date when a task was created.

CV

public static final Key<Double,Byte> CV

The difference between the baseline cost and total cost for a task. Cost Variance = Cost - Baseline Cost

DEADLINE

public static final Key<Date,Byte> DEADLINE

A target date that indicates when a task is to be completed.

DISPLAY_AS_SUMMARY

public static final Key<NullableBool,Byte> DISPLAY_AS_SUMMARY

Determines whether the task should be displayed as a summary task.


Reading supported for XML format only.

DISPLAY_ON_TIMELINE

public static final Key<Boolean,Byte> DISPLAY_ON_TIMELINE

Specifies whether a task should be displayed on a timeline view.

DURATION

public static final Key<Duration,Byte> DURATION

The total span of active working time for a task as entered or as calculated by Microsoft Project based on start date, finish date, calendars, and other scheduling factors.

DURATION_FORMAT

public static final Key<Byte,Byte> DURATION_FORMAT

Task duration format.

DURATION_TEXT

public static final Key<String,Byte> DURATION_TEXT

Returns the task’s duration text.

DURATION_VARIANCE

public static final Key<Duration,Byte> DURATION_VARIANCE

The difference between the baseline duration of a task and the total duration (current estimate) of a task.

EARLY_FINISH

public static final Key<Date,Byte> EARLY_FINISH

The earliest date that a task could possibly finish, based on early finish dates of predecessor and successor tasks, other constraints, and any leveling delay.

EARLY_START

public static final Key<Date,Byte> EARLY_START

The earliest date that a task could possibly begin, based on the early start dates of predecessor and successor tasks and other constraints.

EARNED_VALUE_METHOD

public static final Key<Integer,Byte> EARNED_VALUE_METHOD

Determines whether the % Complete or Physical % Complete field should be used to calculate budgeted cost of work performed (BCWP).

EXTERNAL_ID

public static final Key<Integer,Byte> EXTERNAL_ID

If a task is an external task it contains the task’s external Id.

EXTERNAL_TASK_PROJECT

public static final Key<String,Byte> EXTERNAL_TASK_PROJECT

The source location and task identifier of an external task.

EXTERNAL_UID

public static final Key<Integer,Byte> EXTERNAL_UID

Contains the external task’s Unique identifier when the task is external.

FINISH

public static final Key<Date,Byte> FINISH

The scheduled finish date of a task.

FINISH_SLACK_TIME_SPAN

public static final Key<TimeDelta,Byte> FINISH_SLACK_TIME_SPAN

The duration (in seconds) between the Early Finish and Late Finish dates.

FINISH_TEXT

public static final Key<String,Byte> FINISH_TEXT

Returns the task’s finish text.

FINISH_VARIANCE

public static final Key<Duration,Byte> FINISH_VARIANCE

The time that represents the difference between the baseline finish date of a task or assignment and its current finish date.

FIXED_COST

public static final Key<Double,Byte> FIXED_COST

Shows any non resource task expense.

FIXED_COST_ACCRUAL

public static final Key<Integer,Byte> FIXED_COST_ACCRUAL

Determines choices for how and when fixed costs are to be charged, or accrued, to the cost of a task.

FREE_SLACK_TIME_SPAN

public static final Key<TimeDelta,Byte> FREE_SLACK_TIME_SPAN

The time (in seconds) that a task can be delayed without delaying any successor tasks.

GUID

public static final Key<String,Byte> GUID

The generated unique identification codes for a task.

HAS_OVERALLOCATED_RESOURCE

public static final Key<NullableBool,Byte> HAS_OVERALLOCATED_RESOURCE

Indicates whether the task has an resource assigned which has more work on assigned tasks than can be completed within normal working capacity.

HIDE_BAR

public static final Key<NullableBool,Byte> HIDE_BAR

Determines whether the Gantt bar of a task is hidden when displayed in Microsoft Project.

public static final Key<String,Byte> HYPERLINK

The title or explanatory text for a hyperlink associated with a task.

public static final Key<String,Byte> HYPERLINK_ADDRESS

The address for a hyperlink associated with a task.


The full address (Hyperlink Href in Microsoft Project) of the hyperlink is a concatenation of HyperlinkAddress and HyperlinkSubAddress.

public static final Key<String,Byte> HYPERLINK_SUB_ADDRESS

The specific location in a document in a hyperlink associated with a task.


The full address (Hyperlink Href in Microsoft Project) of the hyperlink is a concatenation of HyperlinkAddress and HyperlinkSubAddress.

ID

public static final Key<Integer,Byte> ID

The position identifier of a task within the list of tasks.

IGNORE_RESOURCE_CALENDAR

public static final Key<NullableBool,Byte> IGNORE_RESOURCE_CALENDAR

Determines whether the scheduling of the task considers the calendars of the resources assigned to the task.

IGNORE_WARNINGS

public static final Key<Boolean,Byte> IGNORE_WARNINGS

Indicates whether to hide the schedule conflict warning indicator in Microsoft Project.

IS_ACTIVE

public static final Key<NullableBool,Byte> IS_ACTIVE

Determines whether a task is active. Inactive tasks no longer affect other tasks or the overall Project schedule.

IS_CRITICAL

public static final Key<NullableBool,Byte> IS_CRITICAL

Determines whether a task is on the critical path.

IS_EFFORT_DRIVEN

public static final Key<NullableBool,Byte> IS_EFFORT_DRIVEN

Determines whether the scheduling for the task is effort-driven scheduling.

IS_ESTIMATED

public static final Key<NullableBool,Byte> IS_ESTIMATED

Determines whether a task is estimated.

IS_EXPANDED

public static final Key<NullableBool,Byte> IS_EXPANDED

Determines whether a summary task is expanded or not in GanttChart view.

IS_EXTERNAL_TASK

public static final Key<Boolean,Byte> IS_EXTERNAL_TASK

Determines whether a task is external.

IS_MANUAL

public static final Key<NullableBool,Byte> IS_MANUAL

Determines whether a task is manually scheduled.

IS_MARKED

public static final Key<Boolean,Byte> IS_MARKED

Shows whether a task is marked for further action or identification of some kind.


Applies to mpp file format only.

IS_MILESTONE

public static final Key<NullableBool,Byte> IS_MILESTONE

Determines whether a task is a milestone.

IS_NULL

public static final Key<NullableBool,Byte> IS_NULL

Determines whether a task is a null task.

IS_OVERALLOCATED

public static final Key<NullableBool,Byte> IS_OVERALLOCATED

Indicates whether any of the assigned resources on a task is assigned to more work on the task than can be done withing the normal working capacity.

IS_PUBLISHED

public static final Key<NullableBool,Byte> IS_PUBLISHED

Determines whether the current task should be published to Project Server with the rest of the project.

IS_RECURRING

public static final Key<NullableBool,Byte> IS_RECURRING

Determines whether a task is part of a series of recurring tasks.

IS_RESUME_VALID

public static final Key<NullableBool,Byte> IS_RESUME_VALID

Determines whether a task can be resumed.

IS_ROLLUP

public static final Key<NullableBool,Byte> IS_ROLLUP

Determines whether information about the subtask Gantt bars will be rolled up to the summary task bar.

IS_SUBPROJECT

public static final Key<Boolean,Byte> IS_SUBPROJECT

Determines whether a task is an inserted project.

IS_SUBPROJECT_READ_ONLY

public static final Key<NullableBool,Byte> IS_SUBPROJECT_READ_ONLY

Determines whether a subproject is read-only.

IS_SUMMARY

public static final Key<Boolean,Byte> IS_SUMMARY

Determines whether a task is a summary task.

LATE_FINISH

public static final Key<Date,Byte> LATE_FINISH

The latest date that a task can finish without delaying the finish of the project.

LATE_START

public static final Key<Date,Byte> LATE_START

The latest date that a task can start without delaying the finish of the project.

LEVELING_CAN_SPLIT

public static final Key<NullableBool,Byte> LEVELING_CAN_SPLIT

Determines whether the resource leveling function can cause splits on remaining work on this task.

LEVELING_DELAY

public static final Key<Duration,Byte> LEVELING_DELAY

The time that a task is to be delayed from its early start date because of resource leveling.

LEVEL_ASSIGNMENTS

public static final Key<NullableBool,Byte> LEVEL_ASSIGNMENTS

Determines whether the leveling function can delay and split individual assignments in order to resolve over allocations.

MANUAL_DURATION

public static final Key<Duration,Byte> MANUAL_DURATION

Defines manually scheduled duration of a task.

MANUAL_FINISH

public static final Key<Date,Byte> MANUAL_FINISH

Defines manually scheduled finish of a task.

MANUAL_START

public static final Key<Date,Byte> MANUAL_START

Defines manually scheduled start of a task.

NAME

public static final Key<String,Byte> NAME

A task’s name.

NOTES_RTF

public static final Key<String,Byte> NOTES_RTF

The text notes in RTF format.


Supported for MPP formats only.

NOTES_TEXT

public static final Key<String,Byte> NOTES_TEXT

Notes’ plain text extracted from RTF data.

OUTLINE_LEVEL

public static final Key<Integer,Byte> OUTLINE_LEVEL

The outline level of a task.

OUTLINE_NUMBER

public static final Key<String,Byte> OUTLINE_NUMBER

The number that represents a task’s position in the hierarchical outline structure.

OVERTIME_COST

public static final Key<BigDecimal,Byte> OVERTIME_COST

The total overtime cost for a task, for a resource on all assigned tasks, or for a resource assignment.

OVERTIME_WORK

public static final Key<Duration,Byte> OVERTIME_WORK

The amount of overtime scheduled to be performed by all resources assigned to a task.

PERCENT_COMPLETE

public static final Key<Integer,Byte> PERCENT_COMPLETE

The current status of a task, expressed as the percentage of the task’s duration that has been completed.

PERCENT_WORK_COMPLETE

public static final Key<Integer,Byte> PERCENT_WORK_COMPLETE

The current status of a task expressed as the percentage of work that has been completed.

PHYSICAL_PERCENT_COMPLETE

public static final Key<Integer,Byte> PHYSICAL_PERCENT_COMPLETE

Percent complete value that can be be used as an alternative for calculating budgeted cost of work performed (BCWP).

PRELEVELED_FINISH

public static final Key<Date,Byte> PRELEVELED_FINISH

The finish date of a task as it was before resource leveling was done.

PRELEVELED_START

public static final Key<Date,Byte> PRELEVELED_START

The start date of a task as it was before resource leveling was done.

PRIORITY

public static final Key<Integer,Byte> PRIORITY

The level of importance given to a task, which in turn indicates how readily a task or assignment can be delayed or split during resource leveling.

REGULAR_WORK

public static final Key<Duration,Byte> REGULAR_WORK

The total amount of non overtime work scheduled to be performed by resources.

REMAINING_COST

public static final Key<BigDecimal,Byte> REMAINING_COST

The remaining scheduled expense that will be incurred in completing the remaining scheduled work.

REMAINING_DURATION

public static final Key<Duration,Byte> REMAINING_DURATION

The time that is required to complete the unfinished part of a task.

REMAINING_OVERTIME_COST

public static final Key<BigDecimal,Byte> REMAINING_OVERTIME_COST

The remaining scheduled overtime expense for a task.

REMAINING_OVERTIME_WORK

public static final Key<Duration,Byte> REMAINING_OVERTIME_WORK

The amount of remaining scheduled overtime time.

REMAINING_WORK

public static final Key<Duration,Byte> REMAINING_WORK

The time still required to complete a task or set of tasks.

RESUME

public static final Key<Date,Byte> RESUME

The date that the remaining part of a task is scheduled to resume after entering any progress.

START

public static final Key<Date,Byte> START

The scheduled start date of a task.

START_SLACK_TIME_SPAN

public static final Key<TimeDelta,Byte> START_SLACK_TIME_SPAN

The duration (in seconds) between the Early Start and Late Start dates.

START_TEXT

public static final Key<String,Byte> START_TEXT

Returns the task’s start text.

START_VARIANCE

public static final Key<Duration,Byte> START_VARIANCE

The time that represents the difference between a baseline start date of a task or assignment and its currently scheduled start date.

STATUS_MANAGER

public static final Key<String,Byte> STATUS_MANAGER

The name of the enterprise resource who is to receive status updates for the current task from resources.

STOP

public static final Key<Date,Byte> STOP

The date that represents the end of the actual portion of a task.

SUBPROJECT_NAME

public static final Key<String,Byte> SUBPROJECT_NAME

The source location of a subproject.

SV

public static final Key<Double,Byte> SV

The earned value schedule variance, through the project status date. Schedule variance (SV) is the difference between the BCWP and the BCWS.

TOTAL_SLACK_TIME_SPAN

public static final Key<TimeDelta,Byte> TOTAL_SLACK_TIME_SPAN

The time a task’s finish date can be delayed without delaying the project’s finish date.

TYPE

public static final Key<Integer,Byte> TYPE

The type of a task.

UID

public static final Key<Integer,Byte> UID

The unique Id of a task.

WARNING

public static final Key<Boolean,Byte> WARNING

Represents the flag which indicates that task has schedule discrepancies.

WBS

public static final Key<String,Byte> WBS

Work breakdown structure (WBS) codes.

WBS_LEVEL

public static final Key<String,Byte> WBS_LEVEL

The rightmost WBS level of a task.

WORK

public static final Key<Duration,Byte> WORK

The total time scheduled on a task for all assigned resources.

WORK_VARIANCE

public static final Key<Duration,Byte> WORK_VARIANCE

The difference between baseline work of a task and the currently scheduled work.