Field | Description |
---|---|
BestPracticeAnalyzer | Shows tasks with no actual work, not assigned tasks, tasks with duration less than 8 hours and summaries assigned with the resources. |
Burndown | Includes work burndown and task burndown charts. |
CashFlow | Shows the costs and cumulative costs per quarter for all top-level tasks. |
CostOverruns | Shows cost variance by task and resource. |
CostOverview | Shows the project\u2019s start and finish dates, the current scheduled and remaining cost, % Complete and cost values for top-level tasks. |
CriticalTasks | Shows project tasks that are critical. |
LateTasks | Shows project tasks that are late. |
Milestones | Shows milestones that are late, coming up and completed. |
OverallocatedResources | Shows the number of remaining work hours for over allocated resources. |
ProjectOverview | Shows the project\u2019s start and finish date, percentage of duration that\u2019s complete, percentage complete for top-level tasks and coming up milestones. |
ResourceCostOverview | Shows baseline, actual, and remaining cost by resource. |
ResourceOverview | Shows baseline, actual, and remaining work by resource. |
SlippingTasks | Shows tasks that are due to finish after their baseline finish dates (baseline must be setInternal). |
TaskCostOverview | Shows baseline, actual, and remaining cost of all top-level tasks. |
UpcomingTask | Shows tasks that are due during the current week and tasks starting during current week. |
WorkOverview | Shows baseline, actual, remaining work for each top-level task and work for work resources. |
BestPracticeAnalyzer
public static final int BestPracticeAnalyzer
Shows tasks with no actual work, not assigned tasks, tasks with duration less than 8 hours and summaries assigned with the resources.
Burndown
public static final int Burndown
Includes work burndown and task burndown charts. The work burndown chart shows how much work people have finished, how much is scheduled to be finished before the project finish date, and the baseline estimate of how much work would be completed at this point in the project. The task burndown chart shows the number of tasks finished, the number remaining, and the baseline estimate of how many would be finished at this point in the project.
CashFlow
public static final int CashFlow
Shows the costs and cumulative costs per quarter for all top-level tasks.
CostOverruns
public static final int CostOverruns
Shows cost variance by task and resource.
CostOverview
public static final int CostOverview
Shows the project\u2019s start and finish dates, the current scheduled and remaining cost, % Complete and cost values for top-level tasks.
CriticalTasks
public static final int CriticalTasks
Shows project tasks that are critical.
LateTasks
public static final int LateTasks
Shows project tasks that are late.
Milestones
public static final int Milestones
Shows milestones that are late, coming up and completed.
OverallocatedResources
public static final int OverallocatedResources
Shows the number of remaining work hours for over allocated resources.
ProjectOverview
public static final int ProjectOverview
Shows the project\u2019s start and finish date, percentage of duration that\u2019s complete, percentage complete for top-level tasks and coming up milestones.
ResourceCostOverview
public static final int ResourceCostOverview
Shows baseline, actual, and remaining cost by resource.
ResourceOverview
public static final int ResourceOverview
Shows baseline, actual, and remaining work by resource.
SlippingTasks
public static final int SlippingTasks
Shows tasks that are due to finish after their baseline finish dates (baseline must be setInternal).
TaskCostOverview
public static final int TaskCostOverview
Shows baseline, actual, and remaining cost of all top-level tasks.
UpcomingTask
public static final int UpcomingTask
Shows tasks that are due during the current week and tasks starting during current week.
WorkOverview
public static final int WorkOverview
Shows baseline, actual, remaining work for each top-level task and work for work resources.