]ResourceAssignment.SplitTask method
Splits task into two parts.
public void SplitTask(DateTime start, DateTime finish, Calendar calendar)
Parameter | Type | Description |
---|---|---|
start | DateTime | The beginning of work interruption to split based on. |
finish | DateTime | The end of work interruption to split based on. |
calendar | Calendar | The calendar to split based on. |
Exceptions
exception | condition |
---|---|
ArgumentOutOfRangeException | Throws when start date is less than the assignment start date. |
ArgumentOutOfRangeException | Throws when finish date is greater than the assignment finish date. |
Examples
Shows how to add a split for a task.
var project = new Project();
// Get a standard calendar
var calendar = project.Get(Prj.Calendar);
// Set project's calendar settings
project.Set(Prj.StartDate, new DateTime(2000, 3, 15, 8, 0, 0));
project.Set(Prj.FinishDate, new DateTime(2000, 4, 21, 17, 0, 0));
// Add a new task to root task
var task = project.RootTask.Children.Add("Task1");
task.Set(Tsk.Duration, project.GetDuration(3));
// Create a new resource assignment and generate timephased data
var assignment = project.ResourceAssignments.Add(task, null);
assignment.TimephasedDataFromTaskDuration(calendar);
// Split the task into 3 parts.
// Provide start date and finish date arguments to SplitTask method which will be used for split
assignment.SplitTask(new DateTime(2000, 3, 16, 8, 0, 0), new DateTime(2000, 3, 16, 17, 0, 0), calendar);
assignment.SplitTask(new DateTime(2000, 3, 18, 8, 0, 0), new DateTime(2000, 3, 18, 17, 0, 0), calendar);
assignment.Set(Asn.WorkContour, WorkContourType.Contoured);
project.Save(OutDir + "CreateSplitTasks_out.xml", SaveFileFormat.Xml);